NCARB ARE 5.0 Practice Management, Programming & Design practice drill
10 realistic exam questions, graded as you go, with the exact rule or statute citation for every answer. Start free, no sign-up.
Sample questions
During negotiation of an owner-architect agreement modeled on AIA Document B101, the owner's legal counsel proposes adding a clause stating that the architect "warrants that the Construction Documents will be completely free of errors and omissions and will reflect the highest possible standard of architectural practice." Why should the architect reject this clause?
It transfers site safety and construction sequencing liability from the contractor to the architect.
It violates state licensing statutes that cap professional liability coverage below construction value.
It elevates liability above the ordinary professional standard of care, creating uninsured contractual exposure.
It eliminates the architect's copyright ownership of the Instruments of Service and prevents billing for Additional Services during construction.
Show the answer
C. It elevates liability above the ordinary professional standard of care, creating uninsured contractual exposure.
Under AIA B101 Section 2.2, the standard of care requires the architect to perform services consistent with the professional skill and care ordinarily provided by architects practicing in the same or similar locality under the same or similar circumstances. Professional liability insurance covers negligence relative to that ordinary standard, not perfection, warranties, or heightened 'highest standard' contractual obligations, which create uninsurable liability.
Reference: AIA Document B101-2017 Section 2.2 / The Architect's Handbook of Professional Practice (AHPP), 15th Ed.
Halfway through Construction Documents on a corporate headquarters project under AIA Document B101, the owner's board cancels the facility because of a corporate merger and issues written notice terminating the agreement without alleging any deficiency in the architect's performance. How does B101 govern this termination?
It is termination for convenience requiring 7 days' written notice and payment for services performed plus Termination Expenses.
It is termination for cause requiring 14 days' written notice and forfeiture of unpaid Reimbursable Expenses.
It is an automatic suspension barring the architect from demobilizing consultants until 90 calendar days have elapsed.
It entitles the architect to collect the entire remaining unearned Basic Services fee for Construction Administration in addition to licensing royalties.
Show the answer
A. It is termination for convenience requiring 7 days' written notice and payment for services performed plus Termination Expenses.
Under AIA B101 Section 9.5, the owner may terminate the agreement for the owner's convenience and without cause upon not less than 7 days' written notice. Under Sections 9.6 and 9.7, the architect is compensated for services performed prior to termination, Reimbursable Expenses then due, and all Termination Expenses directly attributable to termination (such as demobilization and consultant cancellation costs), rather than unearned future fees.
A university needs to renovate an active science laboratory on a tight academic calendar with significant constructability complexity, wants independent architectural advocacy, and requires cost certainty before Construction Documents are complete. Which delivery method best aligns with these goals?
Construction Manager as Constructor (CMaR) with a Guaranteed Maximum Price (GMP).
Design-Bid-Build (DBB) with stipulated-sum bidding after 100% CDs are issued.
Bridging Design-Build with the architect of record contracted under the builder.
Construction Manager as Adviser (CMa) with multiple prime trade contracts and no contractor cost ceiling held by the adviser.
Show the answer
A. Construction Manager as Constructor (CMaR) with a Guaranteed Maximum Price (GMP).
In Construction Manager as Constructor (CMaR / CM at Risk, AIA A133), the owner holds separate contracts with the architect (preserving independent design advocacy) and the CM. The CM provides early preconstruction estimating, constructability review, and fast-track phasing, then converts to constructor at a Guaranteed Maximum Price (GMP) before final CDs are completed.