In a Project Manual organized under CSI MasterFormat, where are bidding instructions, the owner-contractor agreement, and general conditions located versus administrative procedures such as submittal workflows, temporary utilities, and closeout procedures?
- Both bidding rules and submittals belong in Division 00 outside the technical documents.
- Procurement and contracting documents belong in Division 00; administrative and procedural requirements belong in Division 01.
- Bidding instructions belong in Division 01, while submittals and temporary utilities belong in Division 02.
- General conditions and agreement forms belong in Division 01, while Division 00 is reserved for project-specific supplemental drawings and addenda.
Show the answer
B. Procurement and contracting documents belong in Division 00; administrative and procedural requirements belong in Division 01.
Under CSI MasterFormat, Division 00 (Procurement and Contracting Requirements) contains solicitation documents, instructions to bidders, bid forms, the owner-contractor agreement, bonds, and General/Supplementary Conditions. Division 01 (General Requirements) is the first division of the Specifications and governs administrative and procedural work rules that apply across all technical divisions—including summary of work, submittal procedures, quality requirements, temporary facilities, and project closeout.
Reference: CSI Project Resource Manual (PRM) / CSI MasterFormat Divisions 00 & 01