Sample questions
In a Project Manual organized under CSI MasterFormat, where are bidding instructions, the owner-contractor agreement, and general conditions located versus administrative procedures such as submittal workflows, temporary utilities, and closeout procedures?
Both bidding rules and submittals belong in Division 00 outside the technical documents.
Procurement and contracting documents belong in Division 00; administrative and procedural requirements belong in Division 01.
Bidding instructions belong in Division 01, while submittals and temporary utilities belong in Division 02.
General conditions and agreement forms belong in Division 01, while Division 00 is reserved for project-specific supplemental drawings and addenda.
Show the answer
B. Procurement and contracting documents belong in Division 00; administrative and procedural requirements belong in Division 01.
Under CSI MasterFormat, Division 00 (Procurement and Contracting Requirements) contains solicitation documents, instructions to bidders, bid forms, the owner-contractor agreement, bonds, and General/Supplementary Conditions. Division 01 (General Requirements) is the first division of the Specifications and governs administrative and procedural work rules that apply across all technical divisions—including summary of work, submittal procedures, quality requirements, temporary facilities, and project closeout.
While coordinating a commercial tenant build-out specification under CSI MasterFormat, an architect must assign (1) elastomeric joint sealants and fluid-applied air barriers, (2) hollow metal frames, glazing, and door hardware, and (3) gypsum board assemblies and acoustical panel ceilings. Which division mapping is correct?
Division 06 for sealants and air barriers, Division 07 for door hardware and glazing, and Division 08 for gypsum board and ceilings.
Division 05 for hollow metal frames, Division 07 for gypsum board and sealants, and Division 09 for glass glazing and architectural hardware.
Division 07 for glazing and door hardware, Division 08 for air barriers and roofing, and Division 09 for gypsum board and exterior cladding.
Division 07 for sealants/air barriers, Division 08 for frames/glazing/hardware, and Division 09 for gypsum/ceilings.
Show the answer
D. Division 07 for sealants/air barriers, Division 08 for frames/glazing/hardware, and Division 09 for gypsum/ceilings.
In CSI MasterFormat: Division 07 (Thermal and Moisture Protection) covers waterproofing, air barriers, insulation, roofing, flashing, firestopping, and joint sealants; Division 08 (Openings) covers doors, hollow metal/aluminum frames, windows, curtain walls, glazing, and door hardware; and Division 09 (Finishes) covers gypsum board, plaster, tile, acoustical ceilings, resilient flooring, carpeting, and painting/coatings.
A custom millwork subcontractor submits shop drawings that quietly substitute a thinner laminate core than specified in the Project Manual without flagging the deviation in writing. The contractor stamps them approved and forwards them to the architect, who stamps them "Reviewed — No Exceptions Taken." During installation, the panels warp. Under AIA A201, who bears responsibility for the nonconforming material?
The architect, because stamping a shop drawing converts the submittal into a binding Contract Document that supersedes the specifications.
The contractor, because shop drawings are not Contract Documents and unflagged deviations remain the contractor's responsibility.
The owner, because accepting submittals during Construction Administration waives the right to enforce original specification thickness.
The architect and contractor split liability equally because A201 assigns joint responsibility for verifying field dimensions and product thicknesses.
Show the answer
B. The contractor, because shop drawings are not Contract Documents and unflagged deviations remain the contractor's responsibility.
Under AIA A201 Sections 3.12.4, 3.12.8, and 4.2.7, shop drawings are not Contract Documents. The architect's review is conducted for the limited purpose of checking conformance with information given and the design concept expressed in the Contract Documents—not to verify dimensions, quantities, or catch concealed substitutions. The contractor is not relieved of responsibility for deviations from the Contract Documents unless the contractor specifically informed the architect in writing of the deviation at the time of submittal AND the architect gave written approval.